Armenia 500 Tons/Day Copper-Lead-Zinc Ore Beneficiation Project

Date: 2026-02-28 Categories: Client Cases Views: 11

The 500-ton/day copper-lead-zinc ore beneficiation project in Armenia adopts a beneficiation process of "two-stage closed-circuit crushing - one-stage autogenous grinding - lead rough concentrate regrinding - preferential flotation - two-stage dewatering", which is suitable for carbonate rock type deposits. The main metallic minerals are galena and sphalerite, and the gangue minerals are mainly diopside.

亚美尼亚500吨/日铜铅锌矿选矿项目

Recommended process flow and technical basis

  1. ‌Crushing and grinding processes
    A two-stage closed-circuit crushing system is adopted, which controls the ore particle size within a reasonable range before it enters the first stage of autogenous grinding, reducing over-grinding and improving energy efficiency. This design has been verified in a 1500t/d project in Armenia and is suitable for medium-hardness carbonate rock ores.

  2. Flotation process: Preferred flotation + regrinding for enhanced recovery‌

    • A flotation process of "one roughing, three scavenging, and three cleaning" is implemented to prioritize the recovery of lead minerals.
    • The lead rough concentrate is regrinded to improve the degree of liberation of individual minerals and further increase the concentrate grade.
    • The flotation recovery rate can reach 90.49%, the lead concentrate grade reaches 78.85 g/t, and the raw ore grade is 5.61 g/t.
  3. Dehydration process
    Using a disc vacuum filter for concentrate dewatering achieves a dewatering rate of over 95%, ensuring stability during transportation and storage.